In 2014, an LLC tied to Jeff Greene paid $1.5 million for 1.6 acres at 2085 North Flagler Drive, across from Currie Park and a few blocks east of Northwood Village. In June 2026, The Real Deal reported that David Martin's Terra and BH Group were set to buy the same land for about $100 million. They plan two 31-story towers with 281 condominiums. Over those 12 years, the expected price of living on that ground went up about 66 times.
Buyers comparing condos on this stretch of West Palm Beach are pricing that change, whether they mean to or not. On the 1700 to 2500 blocks of North Flagler, an older building sells for a fraction of what a new tower asks. That discount mostly pays for the years when cranes go up on either side of it. The land under the older building, meanwhile, is being valued against the towers next door. The decision is less about old versus new and more about which part of the 2026 to 2029 construction sequence a buyer wants to own.
A listing shows a floor, a view and a price as if all three were fixed. On North Flagler, each address is also a spot in a schedule. Here is the stretch from south to north, using the most recent dates the developers and the city have published.
| Address | Project | Scale | Where it stands |
|---|---|---|---|
| 1717 N. Flagler Dr. | The Ritz-Carlton Residences, West Palm Beach, by Related Group and BH Group | 27 stories, 138 residences averaging 2,500 sq ft | Under construction; completion expected Q2 2028 |
| 1801 N. Flagler Dr. | Flagler Pointe | 9 stories, about 25 years old | Existing building between the new towers |
| Former Temple Israel site | Shorecrest, by Related Ross | 28 stories, 98 residences | Broke ground April 2026; developer expects completion in 2027 |
| 1919 N. Flagler Dr. | Olara | 26 stories | Rising |
| 1830 N. Dixie Hwy. and Pine Street parcels | Pine Street Residences, by The Allen Morris Company with Savanna | 14 stories, 315 rentals | Construction anticipated Q4 2027, completion targeted Q4 2029 |
| 2001 N. Flagler Dr. | Rosewood Residences, by Related Group and BH Group | 27 stories, 90 residences averaging about 3,400 sq ft | Approved by the city in June 2026 |
| 2085 N. Flagler Dr. | Terra and BH Group towers | Two 31-story towers, 281 condos | Planned |
| 2400 N. Flagler Dr. | Currie Park | 13 acres, $35.5 million redesign | Under construction; first phase anticipated to reopen spring 2027 |
The table shows that this corridor will not finish all at once. The work arrives in waves. Shorecrest and the first phase of Currie Park are scheduled for 2027. The Ritz-Carlton follows in the second quarter of 2028, and the Pine Street rental tower is targeted for late 2029. Rosewood and the Terra towers are on paper now, and their construction years have not started. A buyer who closes this winter on a resale unit near 1800 North Flagler is buying three or so years of active building sites. A buyer who reserves at a new tower is buying the same street from the other end, after most of the cranes come down.
The size of the price gap is easiest to see from one block. Flagler Pointe at 1801 North Flagler is a nine-story building about 25 years old. Directly north, the Palm Beach Post reported in April 2026 that Shorecrest residences were priced from $2.7 million to $7 million, with every unit facing the water. The two buildings share an Intracoastal view and a curb. They will not share a building age, an amenity program or a stretch of construction.
A Stet News report of Nov. 13, 2026, shows what living through those construction years means. Three buildings totaling 81 stories are rising on a two-block stretch around Flagler Pointe. Residents described vibration, backup beeping and construction parking spilling into nearby streets. A reading taken from one eighth-floor balcony averaged 75 decibels. City Commissioner Cathleen Ward, whose district includes the building, told Stet News that "this situation isn't normal" and said she had asked city staff whether anything could be done. Planning Board Chair Steve Mayans pointed out in the same report that these conditions are temporary, and that some of today's complaining residents live in towers that drew similar objections when they went up.
Ward and Mayans are describing the same thing from two sides, and the developers' completion dates put a horizon on it. A resale buyer who can live with those years, or who plans to use the unit mainly after 2028, is getting a discount for a cost that falls mostly on whoever owns the unit now. A buyer who needs a quiet morning terrace this season is paying for exactly what they need by choosing a finished tower somewhere else.
The same Stet News report also notes that once the neighboring buildings are complete, Flagler Pointe's wide waterfront views will be permanently different. For an older building on this street, the view a buyer tours in November 2026 is not the view they will have in 2029. Before pricing a resale unit here, stand on its balcony and look at what is going up on each side.
Construction noise is the short-term part. The long-term part is what the new towers do to the value of the dirt beneath older ones, and there are three data points on this corridor.
The first is Greene's parcel, from $1.5 million in 2014 to a reported $100 million in 2026. The second is next door at 2001 North Flagler. Related Group and BH paid $34 million for that site in 2024 and received city approval for Rosewood Residences this June. The third is an older building rather than a vacant lot. La Fontana, a 140-unit, 10-story co-op at 2800 North Flagler completed in 1961, marketed itself for a bulk sale at about $200 million, or roughly $1.4 million per unit. The Real Deal reported on Oct. 20, 2026, that Chuck Whittall's Unicorp National Developments ended its contract on the eve of the deposit going nonrefundable. The co-op's broker said multiple developers remain interested in the site.
The deal fell through, but the asking price still says something. A 65-year-old building on North Flagler set its value per unit by asking what a developer would pay for the land, and the answer had nothing to do with the age of its kitchens. The Real Deal ties this to a shortage of undeveloped waterfront land and to unit owners who are more willing to sell, and it adds that these buyouts are complex and hard to close. For a buyer, that means an older building on a large waterfront site has a second possible value besides its next resale. That value is uncertain and slow to realize, and it should not be counted on. It still belongs on the list.
The other side of the trade is what the corridor becomes once the cranes are gone. The city's redesign of Currie Park, at 2400 North Flagler, is a 13-acre project scheduled to reopen its first phase in spring 2027. Community Redevelopment Agency Executive Director Christopher Roog told the Palm Beach Post the plans include food and beverage options, shade trees and landscaping. The Real Deal reported in June 2026 that Greene reached a land-swap agreement with the city in February that would let Currie Park expand north, alongside his plans for two nearby luxury towers.
To the west, the city lists The District at Northwood, with 382 apartments and 63,000 square feet of commercial and retail space, as under construction near Northwood Village. The Real Deal traces the village's history back to the 1920s, when it was one of West Palm Beach's first commercial districts.
A resale buyer who holds on through 2029 should, if the schedules hold, end up next to a rebuilt Currie Park and a Northwood Village with hundreds of new neighbors at The District. They will have paid an older-building price for it, and absorbed the construction years to get there. A pre-construction buyer pays today for that finished street and gets a new building with it. Both buyers are betting on the same outcome. They pay at different times and carry different costs while they wait.
Does the 2027 Shorecrest date mean construction near 1800 North Flagler ends in 2027? No. The Ritz-Carlton Residences at 1717 North Flagler expects completion in the second quarter of 2028. Pine Street Residences, one block west on Dixie Highway, targets a construction start in late 2027 and completion in late 2029. Read each block's dates separately.
How does this corridor compare with the new towers south of downtown? The price points are different. The Palm Beach Post reported in April 2026 that sales at South Flagler House had reached about $6,000 per square foot, double its opening pricing. North Flagler is earlier in the same cycle. Our look at how new waterfront projects are redefining West Palm Beach luxury covers the broader pipeline, and Olara has its own project page.
Which older buildings have the most at stake? The ones in the middle of active construction blocks, and the ones on large waterfront sites. The first group feels the construction years most. The second group has the most land value for a developer to price, as La Fontana's asking price showed.
If you are weighing a resale unit against a reservation on North Flagler, The Costello-Deitz Group can go through the block-by-block calendar with you, building by building and floor by floor, so you know which years you are buying into before you sign. Contact us for a private consultation.